Aaron Moison, Stirling Council’s Engineer (Bridge Officer) writes:
On Monday 27th May we will be installing temporary 3 way traffic lights at the junction of A81 Glasgow Road and B821 Station Road for repair works to Jenny’s Glen Bridge.
These works are expected to take 4 weeks and will involve us dismantling a large section of the downstream masonry to allow us to rebuild a historic bulge that has recently shown movement. The downstream footpath will also need to be excavated to prevent a collapse during our works.
I have attached a location plan for convenience. Signage to give advance notice to road users should be in place this evening.